Summary update for December 2007 to February 2008
Orange Avenue, 5th to Elden Ave., Chula Vista – Install 240'
of 8-inch PVC main, In Progress
360 E Street, Chula Vista – Install 2" service /3/4"
abandonment, December 11, 2007
Davidson Street Pipeline Replacement Program west of 5th Avenue,
Chula Vista, December 17, 2007
5th Avenue, 325’ north of K Street to 250’ south of Sierra Way,
Chula Vista – Install 547’ of 12-inch PVC and 561-feet of 12-inch
PVC, December 17, 2007
28th Street, F Avenue to Highland Avenue, National City –
Install 663-feet of 8-inch PVC and 52-feet 8-inch PVC, March 3, 2008
Conduit Road, off Kimball Line, Bonita – Install 150’ of
8-inch PVC main, February 4, 2008
(Daily construction time for projects are generally from 7:00 a.m. to
4:00 p.m.)